A busy Friday on site at Apollo. The 2nd floor is being textured.
We will paint out 2nd floor on Monday.
Millwork is being delivered. A photo of the unit entry doors.
The elevator shaft is complete.
The masons are now prepping the 1st wall for the brick veneer.
The remaining 4th floor units in the middle wing are being framed out.
The mortar for the brick veneer is being delivered.
The 1st truck of roof trusses for the middle wing is being delivered.
MGE is putting the permanent gas service into the building.