Aluminum entry doors are being installed.
Tuesday, June 30, 2015
Friday, June 26, 2015
Tuesday, June 23, 2015
Friday, June 19, 2015
Project Update
A busy Friday on site at Apollo. The 2nd floor is being textured.
We will paint out 2nd floor on Monday.
Millwork is being delivered. A photo of the unit entry doors.
The elevator shaft is complete.
The masons are now prepping the 1st wall for the brick veneer.
The remaining 4th floor units in the middle wing are being framed out.
The mortar for the brick veneer is being delivered.
The 1st truck of roof trusses for the middle wing is being delivered.
MGE is putting the permanent gas service into the building.
Tuesday, June 16, 2015
Update
4th Floor - Middle Wing exterior walls are up
4th floor wood floors are going in
The elevator shaft is being installed
4th floor unit separation walls are going up
A view off the end of the 4th floor
North Wing Update
3rd and 4th floor have been painted out. All accent painting is complete. Lightweight floors have also been poured.