Friday, May 30, 2014

Update

The middle wing - 1st floor walls are built and we will swing the 2nd floor trusses next week. Yesterday the 4th floor trusses were set and we will begin sheathing the floor today. 


Friday, May 2, 2014

May Update


The 2nd floor of the north wing is going up and finalizing the grade in the parking before the pre-cast comes on Monday. 



















Monday, March 24, 2014

Pre-Cast

The pre-cast is starting to be set. It will take about 6 days to set the first part of the building. We are also working on finishing the 2nd portion of the foundation. 




Sunday, March 9, 2014

The foundation continued.

Another large section of the foundation has been poured. Will start the wall opposite on Monday. 


Thursday, February 27, 2014

Foundation Update


The first section of the foundation is poured and forms are stripped. 





Tuesday, February 25, 2014

Sunday, February 16, 2014

Apollo Update

The Apollo is well underway. The 1st wing of the foundation is excavated, footing formed, 
and ready to be poured on Monday. The parking lot base is also going in.