Thursday, May 21, 2015

Update

3rd floor trusses are set in the middle wing. 4th floor is being drywalled. 2nd and 3rd floor are being insulated. 


















Monday, May 18, 2015

Apollo

North Wing - 4th floor is insulated and preparing to insulate 3rd later this week. 




Middle Wing - 2nd floor almost all walls are built and preparing to swing 3rd floor trusses later this week. 










Thursday, May 7, 2015

Update

North Wing - most windows and patio doors are set. Should start insulating late next week. 



Middle Wing - 2nd floor is sheathed and exterior walls are being built. 




Thursday, April 23, 2015

Middle Wing

All exterior hallway walls and party walls are built in the middle wing. Preparing to set second floor trusses next week Wednesday. 


North Wing

After 1 day half of the roof is complete. 






Wednesday, April 22, 2015

North Wing

Everything is prepped and the roof is starting to go on the north wing.


Tuesday, April 14, 2015

North Wing

Roof trusses are prepped and ready to swing. Windows are starting to go in. 




The first floor exterior walls of the middle wing are built.