Tuesday, April 14, 2015

North Wing

Roof trusses are prepped and ready to swing. Windows are starting to go in. 




The first floor exterior walls of the middle wing are built. 











Tuesday, April 7, 2015

North / Middle Wing

The 4th floor exterior walls in the North Wing are tipped up and we are working on interior walls.
We should be swinging roof trusses early next week.
The plumbers, electricians and HVAC contractors have started roughing in the building.



 


 

 
Middle Wing exterior walls are being built.





MGE is getting the conduit ran for the electrical service.
 

 

 

Friday, April 3, 2015

North Wing

The 4th has been sheathed and exterior walls are being built. 

A photo from the 4th floor looking over the rest of the building. Saturday we will snap the lines for the walls of the middle wing to being framing early next week. 


Tuesday, March 31, 2015

Wednesday, March 18, 2015

North Wing

3rd floor trusses are set. We will start sheathing tomorrow. 




Friday, March 13, 2015

North Wing

2nd floor interior walls are being built, 3rd floor trusses being prepped, and concrete stoops are being poured. 

















Monday, March 9, 2015

North Wing Update

The 2nd floor exterior walls are going up on the 2nd floor of the north wing.