Monday, September 28, 2015

Concrete

We are getting the main sidewalks poured and preparing to start pouring the driveway. 



Insulation is complete on 3rd floor of the south wing and we are starting to drywall. 






Tuesday, September 15, 2015

Update

The parking lot curbs are poured. 







The retaining walls are going in by the overhead door. 








Friday, September 11, 2015

Update

Carpet is starting to go in the north wing units. 



Sidewalk and curbs are getting ready to go in. 



The exterior is moving along.