Thursday, April 23, 2015

Middle Wing

All exterior hallway walls and party walls are built in the middle wing. Preparing to set second floor trusses next week Wednesday. 


North Wing

After 1 day half of the roof is complete. 






Wednesday, April 22, 2015

North Wing

Everything is prepped and the roof is starting to go on the north wing.


Tuesday, April 14, 2015

North Wing

Roof trusses are prepped and ready to swing. Windows are starting to go in. 




The first floor exterior walls of the middle wing are built. 











Tuesday, April 7, 2015

North / Middle Wing

The 4th floor exterior walls in the North Wing are tipped up and we are working on interior walls.
We should be swinging roof trusses early next week.
The plumbers, electricians and HVAC contractors have started roughing in the building.



 


 

 
Middle Wing exterior walls are being built.





MGE is getting the conduit ran for the electrical service.
 

 

 

Friday, April 3, 2015

North Wing

The 4th has been sheathed and exterior walls are being built. 

A photo from the 4th floor looking over the rest of the building. Saturday we will snap the lines for the walls of the middle wing to being framing early next week.