North Wing

The exterior walls are going up in the North Wing. Next week 2nd floor trusses will arrive. 






Posted by Jason Schmidt at 7:28 PM No comments:
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest

Monday, February 9, 2015

Framing

The framing has begun on the North Wing. 




Posted by Jason Schmidt at 8:38 AM No comments:
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest
Newer Posts Older Posts Home
Subscribe to: Comments (Atom)

Blog Archive

  • ►  2016 (2)
    • ►  May (2)
  • ▼  2015 (39)
    • ►  December (2)
    • ►  November (1)
    • ►  October (2)
    • ►  September (3)
    • ►  August (3)
    • ►  July (2)
    • ►  June (8)
    • ►  May (3)
    • ►  April (6)
    • ►  March (5)
    • ▼  February (2)
      • North Wing
      • Framing
    • ►  January (2)
  • ►  2014 (17)
    • ►  December (2)
    • ►  August (5)
    • ►  July (1)
    • ►  June (2)
    • ►  May (2)
    • ►  March (2)
    • ►  February (3)
Awesome Inc. theme. Theme images by molotovcoketail. Powered by Blogger.