Tuesday, December 15, 2015

Thursday, December 10, 2015

Pool

The pool deck is complete. We will be installing the rails this week and finishing the inside of the pool in the spring. 




12 masons are laying the brick around the pool deck. 





Thursday, November 12, 2015

Update

 
4th floor units are under going final inspections.
 


 

 

Landscaping is coming around the front of the building.



Thursday, October 29, 2015

Update


The insulation for the entire building will be complete Friday. 


The pool has been poured and is being backfilled. 


The sidewalk out front is being poured and black dirt is getting spread. 



Wednesday, October 14, 2015

Update

The community room fire place is installed. 


The tray ceilings in the community room are built. 


The pool deck walls are being poured. 


One of the bio infiltration ponds are installed. 




Monday, September 28, 2015

Concrete

We are getting the main sidewalks poured and preparing to start pouring the driveway. 



Insulation is complete on 3rd floor of the south wing and we are starting to drywall. 






Tuesday, September 15, 2015

Update

The parking lot curbs are poured. 







The retaining walls are going in by the overhead door. 








Friday, September 11, 2015

Update

Carpet is starting to go in the north wing units. 



Sidewalk and curbs are getting ready to go in. 



The exterior is moving along. 
















Friday, August 21, 2015

Update

The exterior is coming along pretty well. 






Cabinets and granite are going in 









Friday, August 7, 2015

Middle Wing

The 4th floor is primed and textured - will be painted tomorrow. 



3rd floor is being insulated. Will start drywall tomorrow. 




Wednesday, August 5, 2015

South Wing

3rd floor exterior walls are up. We are getting interior walls built now. Roof trusses to swing on Tuesday. 


Monday, July 6, 2015

Update

The 1st floor wall are going up on the south wing. 




The exterior is moving along on the North Wing.