Wednesday, July 30, 2014

Update

The north wing, floors 2 through 4 are nearly complete with roughing the mechanicals. 

The middle wing, roof trusses being set early next week with the roof going on August 11th

The south wing, 2nd floor deck is on and exterior walls are being built.