Wednesday, December 31, 2014
Monday, December 1, 2014
Pre-Cast Removal
The removal of the pre-cast had begun. We are planning to have it all removed by the end of the week.
Thursday, August 21, 2014
Sunday, August 10, 2014
Fire
Below is a photo take around 8:20 PM Friday, August 8th - 50 minutes after the fire started.
The following photos were taken Sunday morning. The security fence is being installed and the site is being patrolled by the Madison Police Department while the site is under investigation.
The following photos were taken Sunday morning. The security fence is being installed and the site is being patrolled by the Madison Police Department while the site is under investigation.
Friday, August 8, 2014
Tuesday, August 5, 2014
Monday, August 4, 2014
Wednesday, July 30, 2014
Update
The north wing, floors 2 through 4 are nearly complete with roughing the mechanicals.
The middle wing, roof trusses being set early next week with the roof going on August 11th
The south wing, 2nd floor deck is on and exterior walls are being built.
Tuesday, June 24, 2014
Friday, June 13, 2014
Friday, May 30, 2014
Update
The middle wing - 1st floor walls are built and we will swing the 2nd floor trusses next week. Yesterday the 4th floor trusses were set and we will begin sheathing the floor today.
Friday, May 2, 2014
May Update
Monday, March 24, 2014
Pre-Cast
The pre-cast is starting to be set. It will take about 6 days to set the first part of the building. We are also working on finishing the 2nd portion of the foundation.
Sunday, March 9, 2014
Thursday, February 27, 2014
Tuesday, February 25, 2014
Subscribe to:
Comments (Atom)