Wednesday, December 31, 2014

Foundation repairs

The first section of wall has been poured and we are working on the next section. 




Monday, December 1, 2014

Pre-Cast Removal

The removal of the pre-cast had begun. We are planning to have it all removed by the end of the week. 








Thursday, August 21, 2014

Sunday, August 10, 2014

Fire

Below is a photo take around 8:20 PM Friday, August 8th - 50 minutes after the fire started.


The following photos were taken Sunday morning. The security fence is being installed and the site is being patrolled by the Madison Police Department while the site is under investigation.





Friday, August 8, 2014

Update

The middle wing of the roof is getting wrapped for the for roofers to start Monday. 


Third and fourth floors of the north wing are being insulated. 



The parking garage is being poured. 









Tuesday, August 5, 2014

Update

North wing is roughed and ready for insulation. 





South wing 2nd floor exterior walls are going up. 


Monday, August 4, 2014

Middle Wing

Middle wing roof trusses are set and toffee is schedule for the 11th. 


Wednesday, July 30, 2014

Update

The north wing, floors 2 through 4 are nearly complete with roughing the mechanicals. 

The middle wing, roof trusses being set early next week with the roof going on August 11th

The south wing, 2nd floor deck is on and exterior walls are being built. 






Tuesday, June 24, 2014

Construction Update

The 4th floor roof is sheathed and ready for the roof to be dried in tomorrow. 


The middle wing is ready for 3rd floor trusses to be set tomorrow. 








Friday, June 13, 2014

June update

The roof trusses are being set for the North Wing. 


The Middle Wing - 2nd floor trusses are set, floor is sheathed and we are building exterior walls. 


The frost walls have been poured for the pool deck and we are working on forming the rest of the walls. 


Friday, May 30, 2014

Update

The middle wing - 1st floor walls are built and we will swing the 2nd floor trusses next week. Yesterday the 4th floor trusses were set and we will begin sheathing the floor today. 


Friday, May 2, 2014

May Update


The 2nd floor of the north wing is going up and finalizing the grade in the parking before the pre-cast comes on Monday. 



















Monday, March 24, 2014

Pre-Cast

The pre-cast is starting to be set. It will take about 6 days to set the first part of the building. We are also working on finishing the 2nd portion of the foundation. 




Sunday, March 9, 2014

The foundation continued.

Another large section of the foundation has been poured. Will start the wall opposite on Monday. 


Thursday, February 27, 2014

Foundation Update


The first section of the foundation is poured and forms are stripped. 





Tuesday, February 25, 2014