Thursday, May 12, 2016

Monday, May 9, 2016

Pool

The pool has been plastered and we will start to fill it tomorrow morning. 


Tuesday, December 15, 2015

Thursday, December 10, 2015

Pool

The pool deck is complete. We will be installing the rails this week and finishing the inside of the pool in the spring. 




12 masons are laying the brick around the pool deck. 





Thursday, November 12, 2015

Update

 
4th floor units are under going final inspections.
 


 

 

Landscaping is coming around the front of the building.



Thursday, October 29, 2015

Update


The insulation for the entire building will be complete Friday. 


The pool has been poured and is being backfilled. 


The sidewalk out front is being poured and black dirt is getting spread. 



Wednesday, October 14, 2015

Update

The community room fire place is installed. 


The tray ceilings in the community room are built. 


The pool deck walls are being poured. 


One of the bio infiltration ponds are installed.