Tuesday, September 15, 2015

Update

The parking lot curbs are poured. 







The retaining walls are going in by the overhead door. 








Friday, September 11, 2015

Update

Carpet is starting to go in the north wing units. 



Sidewalk and curbs are getting ready to go in. 



The exterior is moving along. 
















Friday, August 21, 2015

Update

The exterior is coming along pretty well. 






Cabinets and granite are going in 









Friday, August 7, 2015

Middle Wing

The 4th floor is primed and textured - will be painted tomorrow. 



3rd floor is being insulated. Will start drywall tomorrow. 




Wednesday, August 5, 2015

South Wing

3rd floor exterior walls are up. We are getting interior walls built now. Roof trusses to swing on Tuesday. 


Monday, July 6, 2015

Update

The 1st floor wall are going up on the south wing. 




The exterior is moving along on the North Wing.  






Wednesday, July 1, 2015

Apollo Update

Below is a short time lapse from today showing the siding progress.