Friday, March 13, 2015

North Wing

2nd floor interior walls are being built, 3rd floor trusses being prepped, and concrete stoops are being poured. 

















Monday, March 9, 2015

North Wing Update

The 2nd floor exterior walls are going up on the 2nd floor of the north wing. 






Monday, March 2, 2015

Update

The 2nd floor trusses in the north wing are set. 


The pre-cast in the middle wing is set and we are working on the plank in the south wing. 





Thursday, February 12, 2015

North Wing

The exterior walls are going up in the North Wing. Next week 2nd floor trusses will arrive. 






Monday, February 9, 2015

Friday, January 23, 2015

North Wing - Pre-Cast

The North Wing pre-cast is complete. 



We are also working on foundation repairs in the middle wing. 




Wednesday, January 21, 2015