Below is a photo take around 8:20 PM Friday, August 8th - 50 minutes after the fire started.
The following photos were taken Sunday morning. The security fence is being installed and the site is being patrolled by the Madison Police Department while the site is under investigation.
Sunday, August 10, 2014
Friday, August 8, 2014
Tuesday, August 5, 2014
Monday, August 4, 2014
Wednesday, July 30, 2014
Update
The north wing, floors 2 through 4 are nearly complete with roughing the mechanicals.
The middle wing, roof trusses being set early next week with the roof going on August 11th
The south wing, 2nd floor deck is on and exterior walls are being built.
Tuesday, June 24, 2014
Friday, June 13, 2014