The middle wing - 1st floor walls are built and we will swing the 2nd floor trusses next week. Yesterday the 4th floor trusses were set and we will begin sheathing the floor today.
The pre-cast is starting to be set. It will take about 6 days to set the first part of the building. We are also working on finishing the 2nd portion of the foundation.